Building Approval Process
Step 1
Racine County approval
Step 2
Review by the Caledonia Engineering Staff
Allow 2-3 weeks for review by the Village Engineering Department staff, including submission of revised plans. Plans are taken up for review in the order they are received.
Step 3
Drainage Commission approval
- The Drainage Commission meets the 2nd Tuesday of the month. Plans must be received by the Engineering Department 3 weeks prior to the Drainage Commission meeting to allow sufficient time for review.
Step 4
Planning Commission approval
- The Caledonia Planning Commission meets on the last Wednesday of the month. Plans must be approved by the Drainage Commission before the will be considered by the Planning Commission.
Step 5
Village board approval
- The Village Board meets on the 1st and 3rd Tuesday of the month. Plan must have been approved by Racine County, the Drainage Commission and the Caledonia Planning Commission before they will be considered by the Village Board.
Step 6
Building Permit